Back to blog
7 min readFlybyOps Team

Part 107 waiver processing time: how long approval takes

Part 107 waiver processing time varies from weeks to many months. What drives the difference, why applications stall, and how to plan work around it.


Part 107 waiver processing time is the question every operator asks second, immediately after learning a waiver is possible at all. The unhelpful honest answer is that it depends more on what you are asking for and how well you ask than on any queue length. Straightforward requests against well understood provisions can clear in weeks. Requests that push into genuinely novel territory take many months, and a meaningful share never get approved because the safety case underneath them was never built.

This article covers the standard the agency applies, the guidance on how far ahead to apply, what makes one application faster than another, why applications stall, and how to schedule commercial work around a process with no promised turnaround.

The standard the application has to meet

The rule is brief and sets the whole tone. Under 14 CFR 107.200, the Administrator may issue a certificate of waiver authorising deviation from a listed regulation if the Administrator finds the proposed operation can safely be conducted under the terms of that waiver. The request must contain a full description of the proposed operation and a justification establishing that it can be conducted safely. Additional limitations may be prescribed, and the holder may deviate only to the extent specified while complying with every condition attached.

Two words in that provision drive everything about timing. The Administrator must find that the operation can safely be conducted, which means the burden sits entirely with the applicant to supply the evidence for that finding. And the deviation permitted is only what the certificate specifies, so vague applications produce either narrow waivers or none. A request that describes an operation without demonstrating why it is safe has not asked the question the rule requires the agency to answer.

Which rules are waivable, and what that implies

Only the provisions on the published list can be waived, and there are ten of them. They cover operation from a moving vehicle, the anti collision lighting requirement for night operations, visual line of sight, the visual observer requirement, operating multiple aircraft, yielding right of way, operation over people, operation in certain airspace, the general operating limitations including altitude and speed, and operations over moving vehicles. Everything else in Part 107 is not waivable at all, which is worth confirming before an application is drafted. Operators occasionally spend weeks assembling a case for relief from a provision that was never on the list, and the refusal in that situation says nothing about the quality of the safety argument they built.

The list also explains the spread in processing times. A request to operate several aircraft with one pilot in a controlled environment is a bounded problem with established precedent. A request to fly beyond visual line of sight is a request to remove the primary means by which the whole rule set manages collision risk, and the safety case has to replace that function with something the agency can evaluate. The same form, the same rule, and completely different review depth.

Why applications stall

The dominant cause of delay is not queue length but incompleteness. The agency publishes guidance describing what a safety explanation should address for each waivable provision, and applications that work through those points systematically move faster than applications that describe an operation and assert it is safe. Generic text copied from a template is recognisable and unpersuasive, particularly where it fails to engage with the specific hazards of the site and profile being proposed.

The second cause is scope. Applications asking for wide geographic coverage, long validity periods, and multiple deviations at once give the reviewer more to evaluate and more reasons to hesitate. Narrower requests approve faster, and an operator who needs a broad authorization is often better served by establishing a record with a narrow one first. The agency's long standing advice has been to apply at least ninety days before the intended operation, and that figure should be read as a floor for uncomplicated requests rather than an estimate for hard ones.

Scheduling commercial work around an open application

The practical problem is commercial rather than regulatory. A client wants a date, the operation needs a waiver, and nobody can promise when the waiver arrives. Programs that handle this well separate the two conversations: they quote the work that can be flown under existing authorizations with a firm date, and treat the waived portion as a separate phase contingent on approval. Programs that promise a single date for everything end up either flying without the waiver or explaining a slipped deadline. Clients accept a phased schedule far more readily than a missed one, particularly when the reason is an approval nobody controls and the alternative was an operation conducted without it.

Holding waivers before they are needed is the other half of the answer. Operators who identify the deviations their work regularly requires and apply for them during quiet periods build a portfolio that turns future jobs into scheduling questions rather than approval questions. That portfolio needs maintaining, because certificates carry expiry dates and conditions, and a lapsed waiver discovered the week before a job is the same problem as never having applied. The application date, the outcome, the conditions, and the expiry belong on one timeline the whole program can see. Operators running several waivers across several sites lose track of exactly this, and the loss surfaces at the point a client asks which authorization a delivered flight was conducted under.

Common mistakes in applying for a Part 107 waiver

Applying to waive something that cannot be waived. Only ten provisions appear on the list. Confirm the rule you want relief from is on it before investing time in a safety case.

Describing the operation instead of justifying it. The rule requires a justification establishing that the operation can safely be conducted. Description without evidence does not let the agency make the finding it needs to make.

Using template language. Generic safety explanations are recognisable and slow applications down. Engage with the specific site, aircraft, crew, and profile being proposed.

Asking for everything at once. Broad areas, long validity, and multiple deviations lengthen review. A narrow first waiver often gets you flying sooner than a wide one gets you approved.

Forgetting the expiry. Certificates carry validity periods and conditions. A waiver that lapsed between jobs leaves an operation without the authorization everyone assumed was in place.

FAQ

How long does a Part 107 waiver take?

It varies widely by the deviation requested and the quality of the safety case. Uncomplicated requests can clear in weeks, while operations beyond visual line of sight commonly take many months or are refused.

How far ahead should I apply?

The agency's long standing guidance is to apply at least ninety days before the intended operation. Treat that figure as a floor for straightforward requests rather than as an estimate of how long a complex application will take.

Why was my waiver application denied?

Most refusals reflect an incomplete safety case rather than an unacceptable operation. Applications that fail to address the published safety explanation points for the specific rule are the common pattern.

Can I fly while my application is pending?

Not under the deviation you have applied for. Until a certificate of waiver is issued, the underlying rule applies in full, and operating as though approval were granted is a straightforward violation.

Closing thought

The processing time question usually turns out to be a proxy for a planning question, and the planning answer is more useful than any number. Waivers are granted against evidence, so the work of assembling that evidence is the real timeline, and it is work an operator controls. Applying early, asking narrowly, engaging with the specific hazards, and holding the authorizations your work routinely needs before a client asks converts an unpredictable wait into an ordinary piece of program administration.

If you are building a schedule around an FAA approval, FlybyOps was built for the operational record problem at the center of regulated drone work. A document vault tracking authorizations and their expiration dates, a project and job hierarchy linking jobs to the approvals they depend on, a risk register holding the assessments a safety case draws from, and an append-only audit log are all part of how the platform keeps application dates and their outcomes on one timeline a program can plan against.

See it in action

Bring your drone program onto one record

FlybyOps gives enterprise drone teams a single audit-grade record for projects, flights, equipment, risks and incidents. Start free — 14-day trial, no credit card.

Start free trial